Accession Number : AD0600713

Title :   PRODUCTION ENGINEERING MEASURE. PBSE INFRARED DETECTORS-TYPE IR-200.

Descriptive Note : Quarterly progress rept. no. 5, 1 Jan-1 Apr 64,

Corporate Author : SANTA BARBARA RESEARCH CENTER GOLETA CALIF

Personal Author(s) : Cook,G. H.

Report Date : 27 MAY 1964

Pagination or Media Count : 71

Abstract : Approval of test facilities was obtained from USAEMSA. Recommended changes to the specifications of SCS-34A were obtained from USAEMSA. The preproduction run was not completed due to schedule delays and processing problems. Several manufacturing and inspection procedures were revised to reflect corrective actions and improvements. Approval was received for the Inspection and Quality Control Plan submitted to USAEMA. Contract schedule extension was requested and granted. (Author)

Descriptors :   (*INFRARED DETECTORS, PRODUCTION), INFRARED EQUIPMENT, MANUFACTURING, QUALITY CONTROL, LEAD COMPOUNDS, SELENIDES

Distribution Statement : APPROVED FOR PUBLIC RELEASE